Lead times for industrial equipment, 2026

How long the big makers take right now. If your project can't wait, send the spec: we find makers worldwide with earlier slots or stock within 48 hours. Free for buyers.

Find capacity

Can't wait? Ask for refurbished or surplus units: tested reconditioned transformers, switchgear, generators, robots and machine tools often ship from stock in weeks, not years. Tick "Refurbished or surplus OK" on the request.

Power transformers

EquipmentLead time (weeks)As ofSource
Large power transformer (US)1282026powermag.com
Generator step-up (GSU) transformer144-1602026wmbdradio.com
Substation transformer 5-50 MVA92-110Jun 2026industrialsage.com
Medium power transformer 10-50 MVA65May 2026electricaltrader.com
Pad-mount transformer 0-5 MVA52-65Jun 2026industrialsage.com
Distribution transformers30Aug 2025eepower.com

Switchgear and breakers

EquipmentLead time (weeks)As ofSource
MV switchgear, 15 kV class66-80Jun 2026industrialsage.com
MV switchgear, 38 kV91-104Jun 2026industrialsage.com
HV circuit breaker125Dec 2025tradersunion.com

Generators and turbines

EquipmentLead time (weeks)As ofSource
Standby diesel genset 25-400 kW26May 2026globalpwr.com
Standby diesel genset 750-1,000 kW39May 2026globalpwr.com
Standby diesel genset 1.25-3.25 MW70May 2026globalpwr.com
Diesel generator over 3 MW100-110Jun 2026industrialsage.com
Natural gas genset 70-500 kW39May 2026globalpwr.com
New large gas turbine (US)about 312Nov 2026fourweekmba.com

UPS and data-center power

EquipmentLead time (weeks)As ofSource
UPS 500-1,500 kVA39-48Jun 2026industrialsage.com

AI memory

EquipmentLead time (weeks)As ofSource
Enterprise DRAM, large orders40-45May 2026comparethecloud.net

Satellite parts

EquipmentLead time (weeks)As ofSource
Rad-hard FPGAs and processorsabout 702026spacenexus.us
Thrusters, tanks and valvesabout 602026spacenexus.us
Reaction wheels and star trackersabout 522026spacenexus.us
Triple-junction solar cells and panelsabout 522026spacenexus.us

Aircraft engine overhauls (shop visit turnaround)

EquipmentLead time (weeks)As ofSource
PW1100G (GTF)45Jun 2026aviationbusinessnews.com
PW4000 / CF618Jun 2026aviationbusinessnews.com
CFM5613Jun 2026aviationbusinessnews.com
V250010Jun 2026aviationbusinessnews.com

Materials

EquipmentLead time (weeks)As ofSource
Inconel 718 bar and sheet28-32Jun 2026exterrajsc.com

Typical waits reported in public sources; your spec, quantity and destination change the real figure. Updated as new sources come in.

Questions

How long is the lead time for a large power transformer?

Large power transformers take about 128 weeks from the big makers in 2026, and generator step-up transformers 144-160 weeks. Smaller substation units run about 92-110 weeks.

How long does medium-voltage switchgear take?

About 66-80 weeks for 15 kV class and 91-104 weeks for 38 kV switchgear in 2026; high-voltage breakers about 125 weeks.

Are refurbished or surplus units an option?

Yes. Reconditioned transformers, switchgear, breakers, gensets, robots and machine tools ship from existing stock, so lead times are much shorter than new units. Tick "Refurbished or surplus OK" on the request and we include tested refurbished and surplus options next to new-build slots.

How can I get equipment sooner?

Send Norynta your spec, quantity, site country and needed-by date. Within 48 hours we send makers worldwide with earlier production slots or stock, their lead time and origin. Free for buyers.